Parliament demands 90-day housing update as flood victims wait in Durban camps

The Portfolio Committee on Human Settlements has ordered the government to report on the backlog of permanent homes for families still living in temporary accommodation after the 2022 KwaZulu-Natal floods.

Editorial illustration of high-angle close-up of a thick stack of cream-coloured briefing papers on a polished mahogany desk
The South African Enquirer · Illustration

The Portfolio Committee on Human Settlements has ordered the government to provide a comprehensive progress report within 90 days on the permanent housing of flood-affected households who remain in temporary accommodation in KwaZulu-Natal.

The directive follows a visit by President Cyril Ramaphosa and Minister Thembi Simelane to the Cornubia Integrated Human Settlements Project in eThekwini Municipality on 29 October 2026, where 113 completed homes were handed over to beneficiaries.

While the handover marked a milestone for families relocated from the 152 O’Flaherty and Dassenhoek Temporary Emergency Accommodation (TEA) sites, the committee’s report, dated 11 November 2026, highlights that significant work remains for those still waiting in facilities such as the Montclair Temporary Relocation Area.

The report, published by the Parliamentary Monitoring Group (PMG), outlines a series of recommendations aimed at accelerating housing delivery and holding authorities accountable for the reconstruction of communities devastated by the April 2022 floods.

Within 90 days of the report’s adoption, the National Department of Human Settlements, the KwaZulu-Natal Provincial Department of Human Settlements and the eThekwini Municipality must submit a detailed schedule with projected completion dates for the anticipated 25,000 units in the Cornubia development. The current phase has seen the completion of 5,688 units, according to the committee delegation.

The committee has also demanded quarterly progress reports detailing the number of households still awaiting permanent accommodation, the status of title deed issuance, and any delays affecting implementation. Additionally, authorities are required to establish mechanisms for ongoing engagement with affected households within 60 days to document and address concerns regarding temporary accommodation and access to services.

During the visit, President Ramaphosa described the handover as a restoration of dignity and hope for families who endured significant hardship. He highlighted Cornubia as a model of integrated human settlement, combining housing with schools, clinics, transport and economic opportunities to reverse apartheid spatial planning.

The committee noted that beneficiaries expressed satisfaction with the quality of the new homes. The development is expected to address both the specific needs of flood-affected households and broader socio-economic challenges through job creation and local enterprise participation.

The report calls for a plan to be submitted within 90 days to maximise local economic opportunities from the development, including targets for local employment and skills development. A further update on public-private partnerships is due within six months.

Source: Parliamentary Monitoring Group (PMG), https://pmg.org.za/tabled-committee-report/6854